Two big pumps that are part of the Littleton Wastewater Treatment Facility’s primary screw pump replacement project have arrived

After months of delays, and coming at about the time of the April 8 fire that destroyed the backup pump system, the two big pumps that are part of the Littleton Wastewater Treatment Facility’s primary screw pump replacement project have arrived. “The first pump arrived on Wednesday last week and the second pump arrived on Wednesday this week,” Doug Damko, director of the Littleton Department of Public Works, said Friday. “Over the next few weeks both pumps will be finished and painted and the mountings prepared to set them in place.” Supply chain problems delayed delivery of the pumps by months.

Photo credit:

https://www.caledonianrecord.com/news/local/after-delay-pumps-arrive-at-littleton-wastewater-treatment-plant/article_2aabaa82-7ca2-5f61-8e9b-e0e063dbc63e.html